Category Archives: 2012 bond

Askew ES bond project year-end update

[photoshelter-gallery g_id=”G0000GAgCthXM4Jk” g_name=”2015-Bond-Askew” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Askew is receiving a new school to accommodate 850 students, with a budget of $26.6 million. Based on stakeholder feedback from the first community meeting held in July, the project team spent time this fall making design modifications.

The design features a two-story building erected on the north side of the property, with the front entrance remaining south-facing on Wood Lodge. The building plans provide for ample natural light, flexible learning spaces, and areas to accommodate outdoor learning opportunities. Many of the trees will be preserved, and the playground will feature a walking/jogging path that will be available for community use.

The second community meeting will be scheduled in the first quarter 2016. Construction is expected to start in the third quarter 2016, and take about 18 months to complete.

Photo gallery of HISD building projects

Askew ES community hears about plans for new school

[photoshelter-gallery g_id=”G0000PmqaHkMzRHs” g_name=”20150729-Askew” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Askew Elementary stakeholders turned out for the school’s first of three bond community meetings on Wednesday, where they heard from the architect and other project team members about initial design plans for a new campus.

Continue reading

HISD Board of Education to consider 7 more contracts under bond program

Recommended contracts represent nearly $223 million in school construction work

The Houston Independent School District Board of Education on Thursday will consider authorizing the district to negotiate contracts with three firms to provide construction manager at risk (CMAR) services on selected bond projects. Continue reading

Design charrette held for Askew, Wharton Dual Language, Young Women’s College Prep

Project Advisory Team (PAT) members for Askew Elementary, Wharton Dual Language Academy, and Young Women’s College Prep Academy (YWCPA) spent two days this week in an intensive workshop to put together preliminary design plans for their new facilities.

Continue reading

Board of Education to consider design contracts for remaining projects under 2012 bond program

Administrators are recommending that the HISD Board of Education authorize the district to negotiate design contracts with 13 firms on the remaining 14 projects within the 2012 bond program.

The latest round of contract recommendations comes ahead of schedule in response to the booming construction market in Houston. Although architect selections for schools in Groups 3 and 4 of the program weren’t slated to take place until next year, the district wanted to move forward as quickly as possible to minimize the impact of escalating construction inflation.

Continue reading