Category Archives: Building Updates

Lamar HS construction nears completion

Construction at Lamar High School is continuing, as allowable under the public health guidelines, with renovations to the original building now 80 percent complete.

The renovation work, designed to preserve the building’s historically significant architecture, included the construction of a new child care wing, welcome center, and updated ROTC and Career and Technical Education classrooms.

The athletic fields — including football, baseball, softball, soccer practice fields — and tennis courts also are underway.

Continue reading

Scarborough ES construction 94 percent complete

Construction at the new Scarborough Elementary School is steadily progressing, despite the district being closed due to the COVID-19 pandemic.

Work on the campus has continued, as allowable under the public health guidelines, with a reduction of the workforce to adhere to social distancing requirements.

The $23 million project is tracking at 94 percent completion, with site work, paving, underground utilities, structural steel, roofing, interior wall systems, and mechanical, electrical, and plumbing installation complete. Exterior wall systems and interior finishes are ongoing.

Continue reading

Yates HS pool construction passes halfway mark

It’s been several years since students at Yates High School had a swim team. But with the completion of the school’s new natatorium set for April, students are one step closer to making that team a reality once again. 

Construction on the school’s natatorium and four-lane practice pool is 55 percent complete. The building’s exterior walls – which feature large garage-style overhead coiling doors that allow fresh air inside and have fencing at each opening to maintain a secure perimeter — were built first to ensure interior pool construction would not be affected by wet weather.  

The pool’s concrete foundation was laid in January, and pool walls are now being constructed. The project is expected to wrap up later this semester. 

Continue reading

Mitchell ES construction 60 percent complete

The new Mitchell Elementary School is more than halfway complete, and the building will be ready for the school’s young leaders to move in this summer.  

The $23 million project is tracking at 60 percent completion with site work, paving, underground utilities, structural steel, and fireproofing complete. Exterior and interior wall systems, roofing, and mechanical, electrical and plumbing installation are ongoing.  

The building is enclosed and interior finishes, such as flooring and ceilings, are expected to begin this quarter, as well as insulation under the building.  

Continue reading

Braeburn ES construction 65 percent complete

Construction at the new Braeburn Elementary School is steadily progressing and the building will be ready for the Bobcats to move in this summer. 

The $30 million project is tracking at 65 percent completion with fireproofing complete and structural steel and mechanical, electrical, and plumbing installation to wrap this quarter. Roofing and interior framing are more than 75 percent complete and paving will be completed this month. 

The building is enclosed and interior finishes, such as flooring and ceilings, are expected to begin this quarter. 

Continue reading

Lamar HS students enjoy first day of school in new building

Gathered outside Lamar High School’s new main entrance, cheerleaders, Rangerettes, and the color guard shook their pompoms to the beat of the music played by the band, welcoming students back to school. 

Inside, the hum of conversation filled the grand hall as hundreds of students peered around the two-story room, admiring the tall glass walls and massive, blue staircase, as they waited for the first bell to ring. 

“The kids walked in wide-eyed saying, ‘It’s beautiful,’” Lamar Principal Rita Graves said, recalling how eager students had been to see the school during last week’s Texan Prep Days. “They’re just really excited to be learning in such a cool place.” 

Continue reading

Interim Superintendent gets sneak peek of new Lamar and Northside

Interim Superintendent Grenita Lathan walked into the new academic building at Lamar High School on Thursday and stopped for a moment to take it all in. 

Standing in the grand hall, Lathan’s eyes widened as she scanned the two-story, glass-paned entry way and massive, bright blue staircase leading to upper floors. 

“This is wonderful,” Lathan said, smiling as she greeted Lamar Principal Rita Graves. 

Continue reading

Two years later: Schools damaged by Hurricane Harvey moving forward

Nearly three feet of water rippled through freshly painted hallways, carrying brightly colored classroom decorations that fell from wet walls. Bookshelves collapsed and spilled its contents, and desks were scattered about by the force of the water.    

It’s been two years since that scenario played out at four HISD elementary schools — Braeburn, Mitchell, Scarborough, and Kolter.  

Just as faculty and staff at each school had prepared for their newest group of students, Hurricane Harvey made landfall on the Texas coast. The storm inflicted damage so significant that students and staff had to be relocated to temporary campuses.  

Continue reading

Construction progressing at new Mitchell ES

Construction on the new Mitchell Elementary School is progressing as the concrete foundation and hollow core planks are now complete.

Crews have begun the erection of the structural steel and site paving is nearly complete.

The campus is one of four elementary schools — Braeburn, Mitchell, Scarborough, and Kolter — being rebuilt as a result of damages sustained in 2017 during Hurricane Harvey.

“Although Harvey tested our resiliency, it also created an opportunity for our community to be blessed with a new school for our very deserving students,” Mitchell Principal Elizabeth Castillo said. “We are so eager as we watch the progress of our building.  With the foundation being poured, we know that our Mitchell 3.0 will be a beacon of hope as we work to revitalize our community after Harvey.”

Continue reading

Steel structure placed in Kolter ES

Construction continues at Kolter Elementary School with structural steel of the new building nearly complete.

Crews will now begin the installation of both the first- and second-floor slabs. Exterior wall framing will begin next month.

“Watching the beams and framing come to life has made all the difference,” Kolter Principal Julie Dickinson said. “It’s so exciting to see a second floor and to begin to visualize learning spaces and common areas. I can’t believe we’re less than a year away from moving into our new school home.”

Continue reading