Construction on 2012 Bond schools continues despite districtwide closure

With most of the country shut down in an attempt to flatten the COVID-19 curve, HISD’s Construction Services — designated an essential service — is continuing to work on school construction across the district.

HISD Construction General Manager Andreas Peeples said construction is expected to continue as allowable under public health guidelines but noted that required public health measures are affecting normal operations.

“We must comply with requirements that individuals must remain at least six feet from any other person,” Peeples said. “This is important, but it does result in inefficiencies in mobilizing labor and materials and a general reduction in labor forces.”

Continue reading

Yates HS pool construction passes halfway mark

It’s been several years since students at Yates High School had a swim team. But with the completion of the school’s new natatorium set for April, students are one step closer to making that team a reality once again. 

Construction on the school’s natatorium and four-lane practice pool is 55 percent complete. The building’s exterior walls – which feature large garage-style overhead coiling doors that allow fresh air inside and have fencing at each opening to maintain a secure perimeter — were built first to ensure interior pool construction would not be affected by wet weather.  

The pool’s concrete foundation was laid in January, and pool walls are now being constructed. The project is expected to wrap up later this semester. 

Continue reading

New Milby HS pool set to open in coming weeks

In a few short weeks, Milby High School students will be able to make a big splash as the school’s new natatorium and four-lane practice pool nears completion. 

The natatorium, which is 98 percent complete, features large garage-style overhead coiling doors that open to allow fresh air inside, with fencing at each opening to maintain a secure perimeter.  

Remaining work includes installation of the gas meter, fencing, timing system, access control, vestibule doors, emergency phone, roof edge, gutter, and downspouts. 

Continue reading

New Bellaire HS tops out as construction moves forward

Construction at Bellaire High School marked a significant construction milestone this month, as the new building reached its topping out point.  

Topping out refers to the act of placing the last steel beam atop a structure’s highest point. Bellaire students, faculty, and alumni celebrated the occasion by signing a large white beam that was then placed above what will become the school’s natatorium. 

“Having the Class of 2020, our faculty, staff, alumni, and friends sign the beam was a wonderful gesture to ensure that all the elements that make a school community will forever be a part of this new building,” Bellaire Principal Michael McDonough said. 

Continue reading

Mitchell ES construction 60 percent complete

The new Mitchell Elementary School is more than halfway complete, and the building will be ready for the school’s young leaders to move in this summer.  

The $23 million project is tracking at 60 percent completion with site work, paving, underground utilities, structural steel, and fireproofing complete. Exterior and interior wall systems, roofing, and mechanical, electrical and plumbing installation are ongoing.  

The building is enclosed and interior finishes, such as flooring and ceilings, are expected to begin this quarter, as well as insulation under the building.  

Continue reading

Braeburn ES construction 65 percent complete

Construction at the new Braeburn Elementary School is steadily progressing and the building will be ready for the Bobcats to move in this summer. 

The $30 million project is tracking at 65 percent completion with fireproofing complete and structural steel and mechanical, electrical, and plumbing installation to wrap this quarter. Roofing and interior framing are more than 75 percent complete and paving will be completed this month. 

The building is enclosed and interior finishes, such as flooring and ceilings, are expected to begin this quarter. 

Continue reading

Madison HS celebrates grand opening in style

Red, white, silver, and blue balloons were artfully arranged into columns and arches alongside a bright red carpet that guided guests to the dining commons, where rows of black chairs were lined up. 

The celebratory décor created a festive atmosphere for the official grand opening of the new Madison High School, built as part of the district’s 2012 Bond Program and opened to students in January 2019. 

“It’s the perfect place to create a better version of ourselves,” Madison Senior Class President and Student Council Vice President Mariana Martinez said of the new school. “We’re really thankful.” 

Continue reading

Construction progressing at new Mitchell ES

Construction on the new Mitchell Elementary School is progressing as the concrete foundation and hollow core planks are now complete.

Crews have begun the erection of the structural steel and site paving is nearly complete.

The campus is one of four elementary schools — Braeburn, Mitchell, Scarborough, and Kolter — being rebuilt as a result of damages sustained in 2017 during Hurricane Harvey.

“Although Harvey tested our resiliency, it also created an opportunity for our community to be blessed with a new school for our very deserving students,” Mitchell Principal Elizabeth Castillo said. “We are so eager as we watch the progress of our building.  With the foundation being poured, we know that our Mitchell 3.0 will be a beacon of hope as we work to revitalize our community after Harvey.”

Continue reading

Steel structure placed in Kolter ES

Construction continues at Kolter Elementary School with structural steel of the new building nearly complete.

Crews will now begin the installation of both the first- and second-floor slabs. Exterior wall framing will begin next month.

“Watching the beams and framing come to life has made all the difference,” Kolter Principal Julie Dickinson said. “It’s so exciting to see a second floor and to begin to visualize learning spaces and common areas. I can’t believe we’re less than a year away from moving into our new school home.”

Continue reading

Construction continues at Scarborough ES

Work is progressing at Scarborough Elementary School with the building foundation and hollow core plank installation now complete.

Installation of the first and second-floor slabs are in progress.

Scarborough is one of four elementary schools — including Braeburn, Mitchell, and Kolter — being rebuilt as a result of damages sustained in 2017 during Hurricane Harvey.

Scarborough Principal Miriam Medina said the news of the construction progress has made the school community feel a sense of anticipation.

Continue reading