Askew ES bond project year-end update

[photoshelter-gallery g_id=”G0000GAgCthXM4Jk” g_name=”2015-Bond-Askew” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Askew is receiving a new school to accommodate 850 students, with a budget of $26.6 million. Based on stakeholder feedback from the first community meeting held in July, the project team spent time this fall making design modifications.

The design features a two-story building erected on the north side of the property, with the front entrance remaining south-facing on Wood Lodge. The building plans provide for ample natural light, flexible learning spaces, and areas to accommodate outdoor learning opportunities. Many of the trees will be preserved, and the playground will feature a walking/jogging path that will be available for community use.

The second community meeting will be scheduled in the first quarter 2016. Construction is expected to start in the third quarter 2016, and take about 18 months to complete.

Photo gallery of HISD building projects