Austin HS construction at 60 percent completion

The new Austin High School soon will have permanent power, marking a significant development for the 2012 Bond project, which is tracking at 60 percent completion. 

The $80.9 million project will feature flexible learning spaces and sound upgrades for the existing auditorium. The new school will also preserve the façade of the original main building, which was constructed in 1937. 

The tilt-wall panels have been raised, the steel structures supporting them have been erected, and the floor slabs have been placed. The first layer of the roofing system has been installed. Transformers and switchgear are set, and wiring has been connected in preparation for permanent power. 