Category Archives: 2012 bond

Bond Oversight Committee tours new Sterling High School construction, reviews first quarter progress

[photoshelter-gallery g_id=”G00005Ik8QRY.Xvk” g_name=”20160426-BOC” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Hard hats and safety vests were required dress for Thursday’s quarterly meeting of Houston Independent School District’s Bond Oversight Committee, which featured a tour of the new Sterling Aviation High School construction site.

The tour began in the school’s airplane hangar, which serves as the centerpiece of the new school as well as its focus on aviation science. The hangar also will serve as a space for students to work on airplanes and their engines, and large viewing windows will allow students and staff to see the hangar from many points, including the main entrance.

“It’s a very impressive looking building. I’m overwhelmed by the size of it,” BOC member Sonny Flores said, as he and fellow committee members entered the three-story, 230,000-square-foot structure.

Continue reading

Construction on the new Lee HS moves forward despite heavy rains

Heavy rain and flooding throughout the Houston area may have slowed down many this week, but construction at the new Lee High School work site continued to move forward.

[photoshelter-gallery g_id=”G0000R5C9v.jNxXM” g_name=”20160415-Lee” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Located on Houston’s west side, the $73.8 million, 240,000-square-foot facility is being rebuilt as a modern learning environment that will accommodate 1,700 to 1,900 students.

“The school looks like it’s going up pretty fast, and I’m really happy given the weather lately,” said Lee Principal Jonathan Trinh. “The community appreciates having a new school. With the neighborhood surrounding the school going through renovations now, we’re hoping the new campus will kick start and revitalize the area.”

Continue reading

Wharton renovation, expansion plans presented to community; construction to start soon

Once construction is complete, the new Wharton Dual Language Academy will feature new learning spaces and labs, a new gym and library, an interior courtyard preserving heritage trees, and a grand, three-story, glass entryway.

Designs plans for the school’s renovation and new addition were detailed to nearly 100 Wharton parents and community members Thursday night during  community meeting at the Wharton campus.

[photoshelter-gallery g_id=”G0000zs1OfpkPbNw” g_name=”20160421-Wharton” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

The project is part of the Houston Independent School District’s 2012 Bond Program, which calls for renovation or replacement of 40 schools across the district. Construction at Wharton is expected to start later this year, with the Montrose-area school expected to re-open its doors in fall of 2018.

The project will expand the school’s capacity up to 900 students and eliminate all the temporary buildings from the site.

Continue reading

Every day counts for Mark White ES building project

[photoshelter-gallery g_id=”G0000xE9v.0CcSHc” g_name=”20160415-White” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

As most of HISD and the City of Houston had a couple of unexpected days off this week because of rain and flooding, construction crews at the new Mark White Elementary School were on the job. With just 124 days until the start of the 2016-2017 school year, the workers know that each day is critical to ensuring that the school is ready in time to welcome students in August.

“It’s definitely a challenge because we are up against a hard deadline, but we have a good team in place working to make it happen,” said Brian Alling, HISD’s project manager of the Mark White Elementary project. “Both the contractor and architect deserve a lot of credit.”

Continue reading

Kashmere High School construction plan approved

The HISD Board of Education unanimously awarded a construction contract that will bring much needed building improvements to Kashmere High School.

Kashmere is joining nearly two dozen schools under construction thanks to the voter-approved 2012 Bond Program. The board awarded Kashmere’s contract to DT Construction for a total cost that will not exceed $14.1 million.

“We are excited to give Kashmere students a campus that reflects the community’s proud history,” said Trustee Rhonda Skillern-Jones, who represents the Kashmere area. “Kashmere is gaining strong momentum academically and this major renovation will further establish the campus as a center of community activity.”

Located on Houston’s northeast side, Kashmere was built in 1969 and last renovated in 2000. Design plans call for the four main campus buildings to be merged into one, and the school’s center courtyard to be enclosed, creating a large indoor flexible space with natural light for year-round use. Plans also include an updated front entrance.

Construction at Kashmere could begin by early summer, with work complete within a year.

The Kashmere community is invited to learn more about the project at a community meeting scheduled for 6:30 p.m. Wednesday, May 18, at Kashmere High School, 6900 Wileyvale Road.

Rusk School redesign approved

Also Thursday, HISD trustees unanimously approved a plan to gradually transition the Rusk School into a middle school campus with a magnet program with a health and medical focus, similar to the Baylor College of Medicine Academy at Ryan. The change is being made in anticipation of the Star of Hope Mission’s impending relocation outside of the current Rusk attendance boundary.

“We are committed to giving Rusk the resources it needs to remain a strong neighborhood school while also providing all HISD students with another great magnet option,” said Trustee Diana Dávila, who represents the Rusk community.

Priority admission will be given to middle school students who live within the current Rusk attendance boundary. Remaining seats will be open to all HISD students using a random lottery.

Under the plan, Rusk will no longer house students in grades Pre-K through 2 after the current school year.  Next school year (2016-2017), Pre-K students living in the current Rusk attendance boundary will be rezoned to the Ninfa Laurenzo Early Childhood Center, and students in grades kindergarten through second will be rezoned to Lantrip and Burnet elementary schools. Grades 3 through 5 will be phased out one grade level at a time over three years, starting with third grade in the 2017-18 school year, with those students also being rezoned to Lantrip and Burnet.

Businesses get customer service tips during Workshop Wednesday

More than three dozen local business owners learned strategies and tips for improving customer service on Wednesday during a monthly workshop hosted by HISD’s Business Assistance Supplier Diversity department.

Customer service expert trainer Mercedes Alfaro spoke to the group, presenting tips for delivering superior customer service and discussing the importance of identifying consumer needs. Alfaro works with companies across the nation, speaking on topics such as management, leadership, communication, diversity sensitivity and customer service.

Continue reading

District’s new career and technical education center at Jordan HS accepting applications

Rising juniors at nine HISD high schools have the opportunity to explore different careers without changing schools, thanks to the district’s first regional career and technical education center at Barbara Jordan.

The Barbara Jordan Career Hub is now taking applications from 10th-grade students zoned to Davis, Furr, Kashmere, North Forest, Reagan, Sam Houston, Washington, Wheatley, and Yates high schools to participate in the specialized program at Jordan, where they will get specialized education and training in high-demand fields.

Continue reading

HISD Board of Education to consider Kashmere High School construction contract

The Houston Independent School District Board of Education on Thursday is expected to consider a construction contract for Kashmere High School, which is undergoing significant renovation as part of the 2012 Bond Program.

The bid for the renovation work was submitted by DT Construction in response to a February request for competitive sealed proposals. The proposal — one of three submitted — includes a base bid of $13 million with a construction contingency of $1.1 million, meaning the total costs would not exceed $14.1 million. Continue reading

Anticipation is growing as Furr High School construction makes progress

[photoshelter-gallery g_id=”G00003afEyy_WVNQ” g_name=”20160411-Furr” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction on the new building for Furr High School is set to be complete just 12 short months from now and open to students for the start of the 2017-2018 school year, project manager Michael Scott confirmed at the school’s quarterly Project Advisory Team meeting last week.

“I’m really pleased with the progress that’s been made in the first quarter,” Scott said. “Despite a couple of rain delays, we’re on schedule and we expect to stay that way.”

Continue reading

Construction on Davis HS campus to begin this summer

[su_youtube_advanced url=”https://www.youtube.com/watch?v=lFsndkzB6lg”]

Work on the bond project to rebuild Davis High School is slated to begin this summer when construction gets underway on a parking lot off Tackaberry Street.

That new lot is part of an expansion plan for the Near Northside campus, and the first step in a three-phase project that will bring two additions and renovations to create a newly modernized school for 1,500 to 1,700 students.

“We’re basically working from the left of the campus to the right,” Architect Mark French of the IBI Group, told more than 40 people who turned out Thursday for a meeting to get the latest updates on the historic school.

Davis Principal Julissa Alcantar-Martinez opened the meeting by thanking the school community, especially the Project Advisory Team, for working together to move the project forward and to advocate for the best facility possible for students.

“They have stuck with this for three years even when it hasn’t been easy,” she said, noting that the school received $19 million in additional funding in December because of that support.

[photoshelter-gallery g_id=”G0000T2MMcPK_Nek” g_name=”20160407-Davis” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Continue reading