High School for Law and Justice project moves into next phase of construction

[photoshelter-gallery g_id=”G0000oXEbJN7u1Ig” g_name=”20160830-HSLJ-Bond” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction crews are beginning to mobilize at the site of the new High School for Law and Justice after receiving a “notice to proceed” from HISD earlier this month.

The notice followed the completion of comprehensive site demolition work and starts the clock ticking on an approximate 17-month construction timeline.

“The planning and preparation takes much longer than the actual construction,” said Spencer Wingate, HISD’s project manager overseeing HSLJ’s new construction. “Everything’s looking good at this point, and we’re on track to meet our target completion date in December 2017.”  Continue reading

Ribbon-cutting ceremony at North Houston Early College HS marks opening of new building

[photoshelter-gallery g_id=”G0000bv70ObhK.Oc” g_name=”20160819-NHECHS” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

North Houston Early College High School held a ribbon-cutting ceremony on Friday to celebrate the opening of their new building, located on the Houston Community College Northeast campus.

“We’re extremely proud of our beautiful, new, state-of-the-art facility,” NHECHS Principal Angela Lundy-Jackson said. “It took so much to get to this point, and I’m so appreciative to everyone who worked tirelessly to make our vision a reality.”

Continue reading

New Mandarin Immersion Magnet School campus near completion, set to open Monday

[photoshelter-gallery g_id=”G0000WmnGKPDBSNM” g_name=”20160727-MIMS” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

The new Galleria-area campus for the Mandarin Immersion Magnet School (MIMS) is nearing completion, and construction crews are working hard to ensure that the building is all set to welcome students for the first day of school on Monday.

Part of the district’s current bond program, the $32.2 million school, located in the 5400 block of W. Alabama adjacent to the School at St. George Place, is one of HISD’s most popular magnet programs, with more than eight applications for every available spot. It draws students from all parts of the district and is one of HISD’s most diverse schools, but it long ago outgrew its initial location on the former Gordon Elementary campus in Bellaire.

Continue reading

Waltrip HS students will enjoy new spaces this school year

[photoshelter-gallery g_id=”G0000BWI9vge_xzc” g_name=”20160811-Waltrip” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

After years of construction, Waltrip High School is now poised to unveil the completion of several major renovations projects when students return to school this fall.

On the first day of school, students are expected to be welcomed by a new main entry and band hall, new first- and second-floor classrooms, new administrative offices, and new career education spaces.

Continue reading

Construction progress on new Milby HS hard to miss

[photoshelter-gallery g_id=”G0000rIVtuW7E5nk” g_name=”20160728-Milby” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

If you haven’t driven by the new Milby High School recently, the progress is hard to miss and it’s even visible from the 610 Loop.

Construction on the new 267,000-square-foot project along Broadway in Houston’s East End is about 65 percent complete and tracking on schedule for a projected summer 2017 opening. The school is a combination of new construction and renovation that preserves the historical front entrance while creating a modern learning environment for up to 2,000 students.

Continue reading

Leland College Prep Academy construction nears halfway point

[photoshelter-gallery g_id=”G0000PaHgDn7CGOM” g_name=”2016-Bond-Leland-Prep” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction on the new Mickey Leland College Preparatory Academy for Young Men, located in Houston’s historic Fifth Ward, has been progressing well over the last quarter, and is now about 50 percent complete.

Part of HISD’s current bond program, the new 139,000 square-foot-facility, located at 1701 Gregg St., will accommodate 900 to 1,000 students once completed in the second quarter of 2017. Continue reading

Bond program features district-wide technology upgrades

 [photoshelter-gallery g_id=”G000004gY.JHMir0″ g_name=”Bond-technology” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

You’ve probably heard about HISD’s $1.89 billion bond program to rebuild or renovate 40 schools across the district. But did you know that $100 million of that funding has been earmarked to upgrade technology infrastructure at all HISD schools?

Once complete, the enhanced digital framework will provide expanded internet access throughout each campus, allowing for the delivery of more robust online instructional resources to classrooms and mobile devices.

“Each school has tablets and laptops available for use in the classroom, meaning that as many as 30 devices are in use in close proximity,” said Lenny Schad, HISD’s Chief Technology Information Officer. “Expanding the district’s Wi-Fi capability at all campuses will allow us to provide sufficient access for a large number of devices and also will support our mobile learning initiative in a cost-effective way.” Continue reading

Board president takes Up Close look at bond program with interim COO

Approved by Houston voters in 2012, HISD’s Bond Program will renovate or rebuild 40 schools across the district, and Interim Chief Operating Officer Lenny Schad shared the latest details during the July episode of Up Close with Manuel Rodriguez.

“This summer is shaping up to be a turning point in the bond program,” Rodriguez said, as he opened his show. “Currently, we have more than two dozen schools under construction, and we are set to open six new schools in August.” Continue reading

Bird’s-eye view of bond construction

School construction is moving forward across the city at a record pace as project teams work to implement the district’s $1.89 billion bond program. With about two dozen projects currently under construction, chances are you’ve seen some of this work in progress.

For a bird’s-eye view of some of the sites, check out these aerial photos taken in May and June.

[photoshelter-gallery g_id=”G0000HLoj9QzeqnQ” g_name=”Bond-Bird-s-eye-view” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

HISD’s voter-approved bond program calls for the rebuilding or renovation of 40 schools, including 29 high schools. Once complete, HISD will have one of the most modern portfolios of high schools in the country.

The bond program also includes projects that will benefit students across the district, including $100 million in technology upgrades, $44.7 million to replace regional fieldhouses and improve athletics facilities, $35 million to renovate middle school restrooms, and $17.3 million for safety and security improvements

Schools set to open in time for the start of the 2016-2017 school year include Condit and Mark White elementary schools, North Houston Early College and South Early College high schools, Mandarin Immersion Magnet School, and (non-bond) North Forest Early Childhood Center.

More information on HISD Building Programs

This summer will mark turning point for bond program

[photoshelter-gallery g_id=”G0000oXXIpU0JNck” g_name=”Bond-Summer2016″ width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Every summer is hectic for HISD’s construction department, but the summer of 2016 is shaping up to be one for the record books as the district’s $1.89 billion Bond Program reaches a critical turning point.

With construction underway at about two dozen campuses and six new school buildings planned to open for the start of the new school year, there has never been a busier time for the district’s building programs.

Continue reading