Category Archives: 2012 bond

New Milby HS eyes summer opening

[photoshelter-gallery g_id=”G0000kPz80n1QHDo” g_name=”20170124-Milby” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]
Construction on the new Milby High School is now 85 percent complete and on track to open in time for summer school.

The three-story $69 million project, part of HISD’s 2012 bond program, is a combination of new construction and renovation that preserves the historical front façade while creating a modern learning environment to accommodate 2,000 students.

Continue reading

Construction progress on new Milby HS hard to miss

[photoshelter-gallery g_id=”G0000rIVtuW7E5nk” g_name=”20160728-Milby” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

If you haven’t driven by the new Milby High School recently, the progress is hard to miss and it’s even visible from the 610 Loop.

Construction on the new 267,000-square-foot project along Broadway in Houston’s East End is about 65 percent complete and tracking on schedule for a projected summer 2017 opening. The school is a combination of new construction and renovation that preserves the historical front entrance while creating a modern learning environment for up to 2,000 students.

Continue reading

Milby HS takes shape as bond construction moves forward

As concrete walls go up and steel framing is erected, the Milby High School community can now see the future of their new campus beginning to take shape.

[photoshelter-gallery g_id=”G0000nKvHpQJFGiM” g_name=”20160407-Milby” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

The 267,000-square-foot project along Broadway Street in Houston’s East End is a combination of new construction and renovation, allowing the school to maintain its historical structure while also creating a modern learning environment for up to 2,000 students.

“All of the tilt walls and concrete walls have now been completed,” said HISD’s Project Manager Mark Crippen. ”It seems as if it takes forever to complete, but once construction starts, it moves pretty quickly.”

Continue reading

With first wall up for new Milby HS, project expected to rapidly take shape

[photoshelter-gallery g_id=”G0000Et6rjfCoyfQ” g_name=”2015-Bond-Milby” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

The Milby High School project reached an exciting milestone in December, when the first wall was raised.

The new structure will now quickly take shape as steel goes up in the coming weeks. The 267,000-square-foot project is a combination of new construction and renovation.

The school will maintain its historical facade along Broadway in Houston’s East End, while creating a modern learning environment for up to 2,000 students.

The new building is slated to open for the 2017-2018 school year.

Photo gallery of HISD building projects

First wall goes up at new Milby High School

[photoshelter-gallery g_id=”G0000K.gyFdHLgXE” g_name=”20151210-Milby” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

The construction work at Milby High School took a major step forward on Thursday when workers lifted the first wall of the new school.

“It’s really a ballet,” said HISD’s Project Manager Mark Crippen. “Once the first wall is up, it just keeps going. That crane can’t stop.”

Milby is among 40 HISD schools being renovated or rebuilt as part of the district’s $1.89 billion bond program. The 267,000 square foot project is a combination of new construction and renovation. The school will maintain its historical façade along Broadway in Houston’s East End, while creating a modern learning environment for up to 2,000 students.

Continue reading

HISD breaks ground on four new campuses, celebrates first project to ‘go vertical’

Two years ago, Houston voters approved a $1.89 billion bond to replace or repair 40 HISD campuses, including 29 high schools. Now, taxpayers are starting to see the fruits of that decision, as HISD officials and community leaders have broken ground on four brand new campuses over the past two weeks, and recognized the first project from the 2012 bond to “go vertical.” Continue reading

Milby Community Learns More About Initial Design Concepts for School

More than 150 parents, teachers, students and alumni of Milby High School turned out Tuesday night to learn more about the preliminary designs and concepts for the new school being funded by the 2012 bond program.

Milby is slated to be rebuilt into a 21st century facility while maintaining the campus’s architecturally significant building structure. On Tuesday, HISD staff and the school’s architects fielded many questions about the project, including size, classrooms and athletic fields.

Continue reading

Furniture Expo Sets Stage for 21st Century Learning Spaces

Sitting down at flexible tables with swivel chairs and tablet compartments, students, teachers and parents moved quickly from one piece of furniture to the next to see which ones were the most comfortable and collaborative.

[photoshelter-gallery g_id=’G0000mPVutrZ5Veg’ g_name=’20131105-Furniture’ width=’600′ f_fullscreen=’t’ bgtrans=’t’ pho_credit=’iptc’ twoup=’f’ f_bbar=’t’ f_bbarbig=’f’ fsvis=’f’ f_show_caption=’t’ crop=’f’ f_enable_embed_btn=’t’ f_htmllinks=’t’ f_l=’t’ f_send_to_friend_btn=’f’ f_show_slidenum=’t’ f_topbar=’f’ f_show_watermark=’t’ img_title=’casc’ linkdest=’c’ trans=’xfade’ target=’_self’ tbs=’5000′ f_link=’t’ f_smooth=’f’ f_mtrx=’t’ f_ap=’t’ f_up=’f’ height=’400′ btype=’old’ bcolor=’#CCCCCC’ ]

More than 70 people tested out furniture on display Tuesday at Houston ISD’s first furniture expo showcasing 21st century learning environments. The event allowed Project Advisory Teams (PATs) to explore different learning spaces and provide feedback to help guide the design for the new schools being built and renovated under the district’s 2012 bond program.

Continue reading

2012 Bond Campuses Using Environmental Design to Keep Schools Safe

At DeChaumes Elementary School, the main entrance to the school is controlled through an intercom system and two sets of locked doors.

The design process has started for the first phase of HISD’s 2012 bond program, and district officials plan to incorporate crime prevention through environmental design on all 40 campuses under the $1.89 billion bond project.

“We’re going to create safe and secure environments for our students and faculty,” HISD’s General Manager for Facilities Planning Sue Robertson said. “That doesn’t mean creating prison-like environments, but including common-sense applications.”

Continue reading

Board of Education to Consider 12 More Contracts for Work Related to 2012 Bond

Selected projects include 10 of the largest high schools slated for construction

Administrators are recommending that the HISD Board of Education authorize the district to negotiate design contracts with 12 firms on a dozen more 2012 bond projects, including 10 of the largest high schools. The projects represent about $750 million in bond dollars.

Continue reading