Tag Archives: 2012 Bon Progra

Mitchell ES construction 60 percent complete

The new Mitchell Elementary School is more than halfway complete, and the building will be ready for the school’s young leaders to move in this summer.  

The $23 million project is tracking at 60 percent completion with site work, paving, underground utilities, structural steel, and fireproofing complete. Exterior and interior wall systems, roofing, and mechanical, electrical and plumbing installation are ongoing.  

The building is enclosed and interior finishes, such as flooring and ceilings, are expected to begin this quarter, as well as insulation under the building.  

Continue reading