This week, HISD joined with more than 20,000 members of Alpha Kappa Alpha Sorority Incorporated to publicly thank them for donating thousands of dollars to district students and staff in the wake of Hurricane Harvey.
Tag Archives: Wanda Adams
Lawson MS hosts ‘Walk to Remember’ before building demolition
Music echoed throughout the Lawson Middle School gym as community members gathered with former students and staff to catch up with old friends, flip through old yearbooks, and dance the afternoon away.
Led by current students and staff, the stroll down memory lane was part of a “Walk to Remember” — an event held to let stakeholders bid their final farewells to the building before it is demolished later this summer.
“It’s important to preserve the memories,” Lawson Principal Kasey Bailey said. “There’s a lot of history with this school, but we’re very excited to move into the new building.”
Madison HS Project Advisory Team tours new school construction
Madison High School Project Advisory Team members joined with school staff for a tour of the Marlins’ new facility, getting a sneak peek of the new gym, dining commons, auto shop, and auditorium.
Construction of the new school is more than halfway complete. The concrete walls have been erected and the installation of the roof, windows, and exterior brickwork is underway. Interior walls are being framed and utility site work is underway.
Permanent power to the building — an important project milestone — will be connected to the building in early May.
New Lawson MS set for completion this summer
Construction on the new Lawson Middle School is now in the final stages, with the project almost 90 percent complete and on track to open this summer.
The main and auxiliary gymnasiums, locker rooms, dining commons, kitchen, and administrative offices are nearly complete, and flooring is being installed throughout the building. In addition, driveways at the east and west sides of the campus are almost finished.
“The end is in sight,” Lawson Principal Kasey Bailey said, noting that furniture selections have been confirmed, and delivery will occur mid-May. “We are extremely excited and can’t wait to move in.”
Parker ES students mark first day in new school
Roaring applause and cheers of joy echoed throughout the Parker Elementary School cafeteria on Monday as Principal Lori Frodine welcomed students to the first day of school in their new building.
To mark the first day, students gathered by grade level for assemblies in the cafeteria, where Frodine excitedly introduced the students to the new facility and its features and answered their questions.
“You guys have the coolest music rooms ever,” Frodine said to the eager students seated before her.
Construction on new Madison HS reaches midway point
Construction on the new Madison High School has now reached the halfway point — a significant milestone for the building project, which is part of HISD’s voter-approved 2012 Bond Program.
Exterior wall installation is nearly finished, and window and roof installation are underway. Brick work has begun on the southeast corner of the building, and fencing is now up along the perimeter of the school’s west parking lot.
Crews also are framing interior walls, installing utilities and flooring, and finishing concrete walls in the auto shop, as well as in locker rooms and restrooms.
New Lawson MS makes steady construction progress
Construction on the new Lawson Middle School is making steady progress, with work now more than 70 percent complete and on track to be finished in the second quarter of 2018.
Walls and ceiling have been installed, and, in the coming weeks, crews will begin painting the gymnasium, locker rooms, and a section of the academic pods. Installation of the theater stage and elevator also are underway, and driveways are being poured on both the east and west sides of the building.
“It’s exciting,” Lawson Principal Kasey Bailey said, noting that she and her staff would be doing a walk-through next week. “Last time they toured the building, it was just a shell. This time they’ll have a more vivid picture of what the spaces will look like since windows, walls, and doors are installed.”
Worthing HS construction making progress
Construction at Worthing High School is quickly advancing, with renovations to the fine arts wing complete and work on the building addition underway.
Crews have renovated the auditorium stage, music rooms, restrooms, locker rooms, and clinic in the existing building. Additionally, the foundation for the new building has been poured and almost two-thirds of the steel framing is in place, with concrete walls for the JROTC and weight room going up.
“This community is ready to see this building, so I’m excited to tell them we’re still on schedule,” Worthing Principal Khalilah Campbell-Rhone said, noting that she was pleased the project timeline had not been impacted by Hurricane Harvey.
New Parker ES on track to open in January
Parker Elementary School will have a new look for 2018, as construction on the new building inches closer to its scheduled December completion.
Exterior brick and roof installations are nearly complete, and steel framing is underway, as is the installation of insulation and dry wall. In addition, building heating and cooling systems are being tested and crews are painting the cafeteria’s exterior.
“I’m extremely anxious, but very excited,” Parker Principal Lori Frodine said. “We’ve been planning for our new school for several years, so it’s wonderful to see it come together. We can’t wait to move in.”
Construction at Lawson MS hits halfway mark
Construction at Lawson Middle School is more than halfway complete with the installation of the roof and testing of the heating and cooling system well underway.
Lawson Principal Kasey Bailey said she’s happy with the construction progress and is looking forward to opening the new school next year.
“I’ve walked the building twice, and it’s definitely coming along,” Bailey said. “Since we are a fine arts magnet, I’m really looking forward to celebrating the arts.”