Category Archives: New schools

Construction on new Yates HS surpasses halfway mark

[photoshelter-gallery g_id=”G0000824JxaG.sPA” g_name=”Yates-HS-12142017″ width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction of the new Yates High School is more than halfway complete, with crews already in the process of installing floors, painting walls, laying pavers, pouring sidewalks, and erecting permanent fencing.

A CenterPoint transformer and meter also has been set, meaning power soon will be connected to the building, allowing crews to begin testing mechanical systems inside the building.

The main entry facing north is nearly complete, with the main entry facing south and building signage soon to follow. The elevator also will soon be installed, and project officials plan to begin ordering new furniture in January.

Continue reading

Austin HS hosts community meeting to discuss temporary campus move

Click to enlarge

Students, faculty, and community members gathered Tuesday in the Austin High School auditorium to learn about the construction plan for their new facility, as well as the logistics of their relocation to a temporary campus.

Austin High School is being re-built as part of HISD’s voter-approved 2012 Bond Program. The $79.6 million project calls for a new facility that accommodates 1,800 to 2,000 students and preserves the architecturally significant structure of the current building.

To accommodate construction and ensure safety, students and staff will relocate to a temporary campus — made up of 15 temporary buildings offering all of the school’s current academic and athletic programs — along S. Lockwood Drive. Students will report to the temporary campus, which is directly behind the current school, when they return from winter break on Jan. 8.

Continue reading

Garden Oaks Montessori additions set for first quarter completion

[photoshelter-gallery g_id=”G00009MhpPIIvAXA” g_name=”20171212-Garden-Oaks-Montessori” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction of two new buildings at Garden Oaks Montessori is nearing the finish line as both structures, as well as the first phase of campus renovations, are scheduled to be complete next quarter.

In the new buildings, external masonry and metal panels have been installed, as have most windows. All interior walls have been inspected and now are being insulated and covered.

Much of the remaining work will focus on interior finishes, including installation of ceiling panels, drywall, doors, and other built-ins.

“It’s been a lot of hard work, but the project has made great progress,” said Garden Oaks Montessori Principal Lindsey Pollock. “We’re planning to move in over spring break, and that’s very exciting.” Continue reading

Wilson Montessori bond construction reaches 75 percent completion

[photoshelter-gallery g_id=”G00009ohmMfOfARo” g_name=”20171117-Wilson-Montessori” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction on Wilson Montessori is nearing the homestretch as work on the school’s new thee-story addition reached 75 percent completion this quarter.

The Montrose-area kindergarten through eighth grade school is receiving a $24.7 million makeover as part of HISD’s voter-approved 2012 Bond program. The project includes construction of a new addition, as well as renovations to the historic facility, which was built in 1924. Continue reading

Austin HS moving to temporary campus in January

Austin High School students and staff will relocate in January to a temporary campus in preparation for the start of construction on their new building.

Construction of the Temporary Learning Center — dubbed by school officials as the “TLC” and made up of temporary buildings — is nearing completion, with plans for students and staff to report to that location on Jan. 8, which is the first day of the spring semester.

The temporary campus was built to ensure student and staff safety during construction. It is located along South Lockwood Drive, directly behind the existing school building.

“It’s becoming a reality. The move is starting to set in,” Austin High School Principal Steve Guerrero said during a recent Project Advisory Team meeting. “It’s still a move, but we’re working to make sure the transition will be as smooth as possible.”

Continue reading

New Westbury HS addition set to open spring 2018

[photoshelter-gallery g_id=”G0000Sny0bDiEAr0″ g_name=”20171013-Westbury-HS-bond” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction on the new addition for Westbury High School is approaching 75 percent completion and on track to open in the second quarter of 2018.

The building is now fully enclosed with permanent power and HVAC systems up and running. Work will continue on exterior masonry and interior finishes into the first quarter.

“I love the new building,” Westbury Principal Susan Monaghan said. “Having the opportunity to walk through and see it room by room has us even more excited. We can’t wait to move in.”

As part of the Houston Independent School District’s 2012 Bond Program, Westbury is receiving a new two-story addition with 26 classrooms, flexible learning centers, two new gyms, and a multi-purpose dining commons area. Continue reading

Foundation at new Madison HS more than halfway complete

[su_vimeo url=”https://vimeo.com/241567188″ width=”640″ height=”480″]

Construction on the new Madison High School is now fully underway, with the foundation two-thirds of the way complete and tilt walls being erected.

Demolition of both the temporary buildings and dugouts have been completed. In addition, the school’s parking lot on White Heather Drive is nearly complete, and site utilities are also being installed.

“I am very excited about the progress and can’t wait to see the finished product,” Madison Principal Orlando Reyna said, mentioning his recent walk-through of the construction site.

Continue reading

Bond Oversight Committee tours Milby HS, hears update on third quarter construction progress

[photoshelter-gallery g_id=”G0000H2A2ekPDca4″ g_name=”20171031-BOC-Meeting-Gallery” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

The Houston Independent School District’s Bond Oversight Committee got an inside look at the new Milby High School while touring the campus as part of their regular quarterly meeting on Tuesday.

The eight-member group got to see 21st century learning in action as they made their way through the dining commons, library, gym, and various classroom spaces, including the welding, science, and culinary arts labs.

They also walked through the large central courtyard and got to see the historic main entrance, which now leads to a park-like green space. Continue reading

Wharton DLA construction project going vertical

Construction of the new Wharton Dual Language Academy is a quarter of the way complete, with interior demolition of the existing building finished and steel framing being erected for the new addition.

Crews are currently pouring concrete on the upper floors of the new three-story addition, as well as installing roofing, plumbing, electrical, and heating and cooling systems within the existing building.

“I’m thrilled to see the new building taking shape,” Wharton Principal Jennifer Day said. “It’s going to be a great new 21st century learning facility for future generations.”

Continue reading

New Kinder HSPVA on track to welcome students in January 2019

[photoshelter-gallery g_id=”G0000ip1ysFK_FM8″ g_name=”20171026-HSPVA” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction on the new Kinder High School for the Performing and Visual Arts in downtown Houston is making steady progress, with work about 65 percent complete as of this quarter.

The $88 million campus, which is part of the Houston Independent School District’s 2012 Bond Program, is located between Caroline and Austin streets near the city’s renowned arts and theater district. It is scheduled to open in January 2019.

After raising the five-story building to its highest point in May, workers have since installed the roof and exterior waterproofing and plan to have the entire building enclosed in the coming weeks. Connection of permanent power will follow, which will enable the air conditioning, heating, and ventilation systems to be up and running by late November. Continue reading