Tag Archives: 2012 bond

Final phase of renovations underway at YWCPA

[photoshelter-gallery g_id=”G0000.R3x4dvA76s” g_name=”20180131-YWCPA” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction at Young Women’s College Preparatory Academy is now 85 percent complete, with first- and second-floor renovations finished and work on third-floor classrooms well underway.

Demolition on the third floor is nearing completion. Ductwork and plumbing have been installed and light fixture replacement and roof installation are in process. In addition, auditorium renovations, including installation of new lighting, ceiling, carpeting, and HVAC system are all underway.

“The space is phenomenal,” YWCPA Principal Dr. April Williams said. “It’s a nice feeling to know that construction will be completed this summer.”

Continue reading

Eastwood Academy starts new year in new addition

[photoshelter-gallery g_id=”G0000dRhvFoOLY9M” g_name=”20180122-Eastwood-Academy” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Eastwood Academy started 2018 with the opening of a new wing — the first of two additions being built for the school as part of the 2012 Bond Program.

Known as the “blue wing,” the building houses the main entrance to the facility, as well as a new student dining and multipurpose area, career and technical education classrooms, an athletics facility, and a large covered patio.

It eventually will connect to the school’s existing two-story classroom wing.

“Our students are enjoying the new amenities, and we already feel at home here,” Eastwood Academy Principal Brandi Lira said. Continue reading

Hundreds turn out to beautify grounds of Hilliard ES after Harvey

[photoshelter-gallery g_id=”G0000kENFIM1WNEc” g_name=”20180129-Hilliard-ES” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Last fall, Hilliard Elementary School was nearly destroyed by Hurricane Harvey. Floodwaters breached the building and pooled in hallways, classrooms, and the cafeteria. At their worst, they rose as high as four feet.

The damage was so severe, students and staff had to relocate so construction crews could carry out a major overhaul of the building.

“Hilliard was wrecked,” HISD Chief Operating Officer Brian Busby said. “It was heartbreaking to see the extent of the damage.”

Five months later, the environment at the elementary school has completely changed — thanks in part to more than 640 volunteers from across the country, all of whom gathered last week at the newly renovated school to beautify the campus grounds. Continue reading

Kashmere HS celebrates grand opening of renovated campus

[photoshelter-gallery g_id=”G0000one45GJHDdM” g_name=”20180123-Kashmere-HS-Ribbon-cutting-ceremony” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Kashmere High School stakeholders gathered Tuesday to celebrate the grand opening of their new 21st century campus, which underwent major renovations as part of HISD’s voter-approved 2012 Bond Program.

Students, staff, alumni, and various dignitaries crowded into the large, brightly lit, central commons area as the nationally acclaimed Kashmere Alumni Reunion Stage Band joined with the dance team and cheerleaders to kick off the festivities. Continue reading

Condit ES receives highest honor in school architecture competition

 [photoshelter-gallery g_id=”G0000DUEVI1Wz.rA” g_name=”20180118-Condit-award” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Condit Elementary School was named Thursday as one of four state recipients of the prestigious 2017-2018 Caudill Award, the highest honor given in the annual Exhibit of School Architecture competition.

Contest judges described the newly built school as a “transformational learning environment” that makes excellent use of its space, reflects the school’s 100-year history, and serves as a showcase campus for the district. Continue reading

Austin HS students move into temporary facility while new campus is constructed

[photoshelter-gallery g_id=”G0000I3x7IzzqgxA” g_name=”20180108-Austin-HS” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Austin High School students and staff began the spring semester on Monday in a temporary campus in preparation for the start of construction on their new building.

The new Temporary Learning Center — dubbed by school officials as the “TLC” and made up of temporary buildings — was built to ensure student and staff safety during construction. It is located along South Lockwood Drive, directly behind the existing school building.

Located in Houston’s East End, the 80-year-old comprehensive high school is being rebuilt as part of the Houston Independent School District’s voter-approved 2012 Bond Program. Plans for the $79.6 million project call for a new facility that preserves the original building’s architecturally significant building structure and can accommodate up to 2,000 students. Continue reading

Renovations wrap up at Scarborough HS

[photoshelter-gallery g_id=”G00007Qnn44IKtFQ” g_name=”20180108-Scarborough-HS” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Scarborough High School senior Melanie Esquivel remembers all too well how often the school band has been shuffled around over the last few years.

They practiced first in the dance hall and then in the gym, but the acoustics amped up their sound so much teachers in nearby classrooms often complained. So they moved into the cramped black box theater, where they made do.

“I almost cried when I saw it. It’s just so emotional. I’ve been waiting so long for it,” the 17-year-old flutist said, hardly able to contain her excitement as she pointed out features of the school’s new band hall. “We’re finally like a big part of the school.”

Continue reading

Robinson ES students return for ‘fresh start’ at home campus after post-Harvey renovations

Children and their parents lined up at the doors of Robinson Elementary School on Monday morning, eager to see inside their newly renovated and repaired school, which sustained significant damage from Hurricane Harvey in August.

As one student stood bewildered looking up and down the hallways, Principal Paige Fernandez-Hohos stepped in. “Who is your teacher? What grade are you looking for?” she asked. After getting the information, Fernandez escorted the little girl down the correct hallway toward the third-grade classrooms.

“It definitely feels like the first day of school in August, just because of the new building and kids aren’t always 100 percent sure of where they are going, and teachers have a new schedule,” Fernandez-Hohos said, noting the help the campus has received in getting ready for the first day back. Continue reading

North Forest celebrates transition into new school with ceremonial walk

Hundreds of North Forest High School students followed Principal Darryl Henson across Mesa Road on Monday, coming together to formally mark their transition into their new school.

The $59.5 million campus is the first new high school built in the North Forest community in almost 50 years.

“It’s important to show our students that we are coming over into a new environment that was built just for them,” Henson said, talking about the importance of the ceremonial walk from the old building to the new one. “I want the kids to feel a sense of pride and ownership.”

Continue reading

New year, new building for Sharpstown HS

[photoshelter-gallery g_id=”G0000g5Or5AhPcWs” g_name=”20180108-Sharpstown-HS” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Lining the sidewalk outside the school, Sharpstown JROTC members lifted their ceremonial swords to the sky while band members played celebratory music to officially welcome their fellow students to their new campus.

Built as part of HISD’s voter-approved 2012 Bond Program, the new school formally opened its doors on Monday. To celebrate the occasion, students and teachers gathered first at their old building and then ceremoniously walked together to the new school. Continue reading