Bond Oversight Committee updated on school construction; 13 campuses set to open

[photoshelter-gallery g_id=”G0000_T9gIi0yhso” g_name=”20180724-BondMeeting” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

The 2018-2019 school year is shaping up to be a busy one for the Houston Independent School District, with 13 new campuses opening next month and five more slated to open in January.

The Bond Oversight Committee learned about the progress of the projects during their quarterly meeting on Tuesday.

To date, the district has opened 27 bond and non-bond projects and expects the current portfolio of building programs to surpass 80 percent completion by the end of 2018. Continue reading

New Washington HS set to open for the 2018-2019 school year

[photoshelter-gallery g_id=”G0000Kv7MEQv.Gcc” g_name=”20180502-BTWashingtonTour” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

When students enter the new Washington High School this fall, they will be greeted by a prominent image of civil rights activist and educator Booker T. Washington.

This year marks the 125th anniversary for the school, which was built in 1893 as the city’s first African-American high school.

Washington Principal Carlos Phillips said he is excited to move into the new school and looking forward to presenting the facility to the community.

Continue reading

Washington HS students create special works of art

[photoshelter-gallery g_id=”G0000SRm_MZM3wbU” g_name=”20180426-BTWashingtonartproject” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

A project for an art class at Booker T. Washington High School has turned into a special gift for a university president on behalf of HISD. Students in Maya Imani Watson’s art class created a piece that highlights the late poet Maya Angelou. The piece will be gifted to Dr. Ruth J. Simmons, the newly minted president of Prairie View A&M University.

Continue reading

Construction on new Washington HS nearing completion

[photoshelter-gallery g_id=”G0000loIpC86CbKw” g_name=”20180123-Washington-HS” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Washington High School students and staff are edging closer to moving into their new building with the construction project now 85 percent complete.

Tile flooring and doors have been installed, as have cabinetry, countertops, and fume hoods in the career and technology classrooms, science and agricultural labs, and computer-aided design spaces. Crews are installing bathroom fixtures and sinks in the science and engineering labs where painting and floor staining also are underway.

In addition, crews are nearly done painting the auditorium and administrative offices and wrapping up installation of the school’s elevator.

Continue reading

Washington HS construction on track for Spring 2018 opening

[photoshelter-gallery g_id=”G0000FSqv1FVa6E8″ g_name=”20171019-Washington-HS” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Construction of the new Washington High School campus is edging closer toward the three-quarter completion mark, with flooring, drywall, ceiling, and window installation all underway.

The $56.5 million project is a part of the voter-approved 2012 Bond Program, which calls for the renovation or rebuilding of 40 schools, including 29 high schools.

Site utility installation for the new school is currently in progress, project officials said. Exterior brick installation is nearly complete, as are the visitor and faculty parking areas. The school’s front bus loop also is more than halfway done.

Continue reading

New Washington HS taking shape as construction progresses


Construction is more than halfway complete at Washington High School, where crews have completed installation of the building’s west side structural steel, exterior concrete walls, and exterior brick.

Crews are making steady progress. Installation of the exterior glass on the $51.7 million facility is underway, and the west side of the building is ready for both paint and flooring.

“It’s exciting to see what’s taking place,” Washington Principal Carlos Phillips said. “This will be the face of our school.”

Continue reading

Washington HS students and staff sign beam for new building 

[photoshelter-gallery g_id=”G00005bwyVc5SA8w” g_name=”20170310-WashingtonSigning” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Students and staff at Booker T. Washington High School had the opportunity on Friday to add their signatures to a steel beam being used in the construction of their new school, which is part of HISD’s 2012 bond program.

“It’s great to see the steel beams and columns going up,” said Washington Principal Carlos Phillips. “We’re happy about the progress and can’t wait to move-in next year.”

Continue reading

Booker T. Washington High School breaks ground on new building

[photoshelter-gallery g_id=”G0000Fb4DCCswyws” g_name=”20160405-Washington” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Booker T. Washington High School celebrated a big milestone Tuesday morning with a festive groundbreaking ceremony to mark the start of construction on a new $51.7 million campus.

More than 100 parents, students, staff, alumni, and community members attended the event and were joined by HISD Trustee Rhonda Skillern-Jones, State Sen. John Whitmire and Houston City Councilwoman Karla Cisneros.

Continue reading

Groundbreaking ceremonies, bond community meetings planned for spring

Two groundbreaking ceremonies, five community meetings and quarterly Bond Oversight Committee meeting scheduled through April

With construction making noticeable progress across HISD, many projects are reaching their next milestone – including including groundbreaking ceremonies at Parker Elementary School and Booker T. Washington High School, and a host of community meetings scheduled for the spring.

Continue reading

Two HISD teachers named finalists for H-E-B Excellence in Education Awards

Two HISD teachers got a big surprise this week, when they learned that they had been named finalists for H-E-B’s 2015 Excellence in Education Awards.

Michael Clark, who was named HISD’s own Secondary Teacher of the Year in 2011, was selected as a finalist in the Lifetime Achievement category at the secondary level, while Dr. Nghia Le, who was recognized by H-E-B in 2011 with the Rising Star Award, was chosen as a finalist in the Leadership category at the secondary level.

[photoshelter-gallery g_id=”G0000JX2Ne3FXHR4″ g_name=”20150312-Le” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ] Continue reading