Category Archives: Building Updates

Delayed opening for four schools being rebuilt due to damage from Hurricane Harvey

The four elementary schools being rebuilt as a result of Hurricane Harvey are now scheduled to open in August 2020 — a three-month delay caused by the COVID-19 pandemic.

Kolter, Braeburn, Mitchell, and Scarborough elementary schools were originally scheduled to open in June 2020.

HISD Construction Services Officer Derrick Sanders said the new timeline is a result of manpower shortages caused by mandated social distancing requirements due to the COVID-19 pandemic.

Continue reading

Bellaire HS construction surpasses halfway mark

Construction at Bellaire High School is now more than 50 percent complete, with the new school expected to be ready for students this time next year.

Crews have installed the roof structure for the new building, which includes wings for academics, fine arts, and physical education. The academic wing is now closed in and air-conditioned, with construction crews currently working on the finishing touches, including tiling and flooring.

Crews also are working on overhead construction in the auditorium high ceilings, digging out the pool and diving well, and construction of the interior walls in the athletics area. Air conditioning is expected to be flowing through the entire building by the end of July.

Continue reading

Construction continues on 2012 Bond realignment projects

Although the Houston Independent School District is closed due to the COVID-19 pandemic, construction work has continued on several 2012 Bond realignment projects across the district.

Realignment projects are new, board-approved projects that were not part of the original scope of work but are funded by surplus bond funds. The projects include natatoriums at Milby, Washington, and Yates high schools, Westbury High School’s fine arts wing, and Sharpstown International School’s dining canopy.

Milby’s natatorium is 98 percent complete. Construction Services is coordinating with HISD Technology and HISD Security Maintenance for remaining minor work. The pool will be ready for the 2020-2021 school year.

Continue reading

Austin HS to open in January 2021 due to COVID-19

The new Austin High School is now scheduled to open in January 2021 — a delay caused by the COVID-19 pandemic.

The school was originally scheduled to open in August 2020. HISD Construction Services Officer Derrick Sanders said the new timeline was due to a three-month delay in the school’s furniture shipment and manpower shortages caused by mandated social distancing requirements resulting from the COVID-19 pandemic.

Austin will remain at its current temporary learning center located across South Lockwood Drive until the new facility opens.

Continue reading

Lamar HS construction nears completion

Construction at Lamar High School is continuing, as allowable under the public health guidelines, with renovations to the original building now 80 percent complete.

The renovation work, designed to preserve the building’s historically significant architecture, included the construction of a new child care wing, welcome center, and updated ROTC and Career and Technical Education classrooms.

The athletic fields — including football, baseball, softball, soccer practice fields — and tennis courts also are underway.

Continue reading

Scarborough ES construction 94 percent complete

Construction at the new Scarborough Elementary School is steadily progressing, despite the district being closed due to the COVID-19 pandemic.

Work on the campus has continued, as allowable under the public health guidelines, with a reduction of the workforce to adhere to social distancing requirements.

The $23 million project is tracking at 94 percent completion, with site work, paving, underground utilities, structural steel, roofing, interior wall systems, and mechanical, electrical, and plumbing installation complete. Exterior wall systems and interior finishes are ongoing.

Continue reading

Yates HS pool construction passes halfway mark

It’s been several years since students at Yates High School had a swim team. But with the completion of the school’s new natatorium set for April, students are one step closer to making that team a reality once again. 

Construction on the school’s natatorium and four-lane practice pool is 55 percent complete. The building’s exterior walls – which feature large garage-style overhead coiling doors that allow fresh air inside and have fencing at each opening to maintain a secure perimeter — were built first to ensure interior pool construction would not be affected by wet weather.  

The pool’s concrete foundation was laid in January, and pool walls are now being constructed. The project is expected to wrap up later this semester. 

Continue reading

Mitchell ES construction 60 percent complete

The new Mitchell Elementary School is more than halfway complete, and the building will be ready for the school’s young leaders to move in this summer.  

The $23 million project is tracking at 60 percent completion with site work, paving, underground utilities, structural steel, and fireproofing complete. Exterior and interior wall systems, roofing, and mechanical, electrical and plumbing installation are ongoing.  

The building is enclosed and interior finishes, such as flooring and ceilings, are expected to begin this quarter, as well as insulation under the building.  

Continue reading

Braeburn ES construction 65 percent complete

Construction at the new Braeburn Elementary School is steadily progressing and the building will be ready for the Bobcats to move in this summer. 

The $30 million project is tracking at 65 percent completion with fireproofing complete and structural steel and mechanical, electrical, and plumbing installation to wrap this quarter. Roofing and interior framing are more than 75 percent complete and paving will be completed this month. 

The building is enclosed and interior finishes, such as flooring and ceilings, are expected to begin this quarter. 

Continue reading

Lamar HS students enjoy first day of school in new building

Gathered outside Lamar High School’s new main entrance, cheerleaders, Rangerettes, and the color guard shook their pompoms to the beat of the music played by the band, welcoming students back to school. 

Inside, the hum of conversation filled the grand hall as hundreds of students peered around the two-story room, admiring the tall glass walls and massive, blue staircase, as they waited for the first bell to ring. 

“The kids walked in wide-eyed saying, ‘It’s beautiful,’” Lamar Principal Rita Graves said, recalling how eager students had been to see the school during last week’s Texan Prep Days. “They’re just really excited to be learning in such a cool place.” 

Continue reading