[photoshelter-gallery g_id=”G0000OIcRm6aNORA” g_name=”20150309-Construction-Gallery” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]
The building site at Sterling High School is buzzing with activity these days as construction is progressing on the school’s new 21st century building.
To date, the drilled foundation piers are 95% complete; the underground electrical, plumbing, storm and sanitary sewer installation is in progress; and the building pad is complete and ready for concrete to be poured in the coming weeks.