Category Archives: 2012 bond

Milestone for 2012 Bond Program as construction gets underway at Bellaire HS

[photoshelter-gallery g_id=”G0000wM1bRk78Ae8″ g_name=”20180702-Bellaire-HS” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Excavators roared to life at Bellaire High School last month, marking the beginning of construction on the new facility and a significant milestone in the 2012 Bond Program, as all remaining projects are now underway.

The first phase of construction — also known as pre-construction — includes installation of underground detention and site utilities, demolition of the Career and Technology Education building, and creation of a temporary parking area to replace the South Rice Boulevard lot, which will become part of the construction site. Continue reading

Hilliard ES home at last after being displaced by Harvey

[photoshelter-gallery g_id=”G0000cSmQyqCo0fM” g_name=”20180626-Hillard” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Hilliard Elementary School has officially moved back to their home campus this week, after being relocated last fall due to flood damage resulting from Hurricane Harvey.

The school — including all classrooms, the library, and the gym — has been completely restored, as have the campus grounds. Additionally, a new retention pond and extensive storm drainage system have been added to prevent future flooding.

Newly appointed Principal Erika Kimble said she is glad to be a part of Hilliard’s new beginning, and is looking forward to working in the renovated building.

“I’m excited about joining the Hilliard family,” Kimble said. “We’ll all get a fresh start together in this beautiful building. I can’t wait to welcome the students back in August.” Continue reading

HISD wins national award for crisis communications during Hurricane Harvey  

District wins 5 NSPRA Golden Achievement Awards and multiple honors for print and digital communications 

The Houston Independent School District Communications team was honored for its crisis communications to families, staff, and the community during Hurricane Harvey – the worst disaster in Houston history – with a Golden Achievement Award from the National School Public Relations Association (NSPRA).

HISD’s Communications team, under the direction of Chief Communications Officer Rebecca Suarez, worked day and night to keep families and the public informed before, during, and after Hurricane Harvey. In addition to local communications efforts, the team also facilitated the dissemination of information on a state and national level.

“Harvey did not stop us, but it made us stronger. Despite the difficulties from the hurricane, we found creative ways to communicate critical and timely information to our students, parents, employees, and the community during one of the worst disasters in local history,” Suarez said. “I’m very proud of my team for the hard work and commitment to putting students first in everything we do.”

Golden Achievement Awards recognize exemplary work in all aspects of school public relations, communication, marketing, and engagement. HISD won a total of five Golden Achievement Awards for the following work:  Continue reading

Building demolition underway at Braeburn ES

[photoshelter-gallery g_id=”G0000aDeg.kiAGXA” g_name=”20180608-Braeburn-Demo” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Demolition at Braeburn Elementary School is underway, with site work and paving soon to follow as crews begin the process of rebuilding the flood-ravaged campus.

“The community is excited to watch as demolition continues and progress on the new building begins,” Braeburn Principal Amanda Rodgers said.

The campus is one of four elementary schools — Braeburn, Mitchell, Scarborough, and Kolter — being rebuilt as a result of damages sustained last year during Hurricane Harvey.

Continue reading

Demolition in progress at Kolter ES

[photoshelter-gallery g_id=”G0000_ePUeVF6Dy8″ g_name=”20180605-Kolter-demo” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

The demolition of flood-ravaged Kolter Elementary School is underway, with site work and building construction expected to start soon after.

Construction is expected to continue through 2019, with the new school opening in early 2020. Students and staff will remain at their current temporary location — the former Gordon Elementary School campus on Avenue B in Bellaire — for the duration of the construction process.

The foreign language magnet is one of four elementary schools — Braeburn, Mitchell, Scarborough, and Kolter — being rebuilt as a result of damages sustained last year during Hurricane Harvey.

Continue reading

Former Mitchell ES currently undergoing abatement

Work has begun at Mitchell Elementary School, where abatement is underway, and demolition is soon to start.

The campus is one of four elementary schools — Braeburn, Mitchell, Scarborough, and Kolter — being rebuilt as a result of damages sustained last year during Hurricane Harvey.

Mitchell’s $23 million facility will accommodate about 750 students. The two-story 91,300-square-foot-building will feature open, brightly colored learning spaces, large windows, abundant natural light, and extended learning spaces throughout the building for individual and group collaboration.

Continue reading

Abatement underway at Scarborough ES

Work has begun at Scarborough Elementary School, where abatement is underway and demolition is soon to start.

The campus is one of four elementary schools — Braeburn, Mitchell, Scarborough, and Kolter — being rebuilt as a result of damages sustained last year during Hurricane Harvey.

Scarborough’s $23 million facility will accommodate about 750 students. The two-story 91,300-square-foot-building will feature open brightly-colored learning spaces, large windows, abundant natural light, and extended learning spaces throughout the building for individual and group collaboration.

Continue reading

Lawson MS hosts ‘Walk to Remember’ before building demolition

[photoshelter-gallery g_id=”G0000lOWbhi4rmRY” g_name=”20180613-LawsonMSTour” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Music echoed throughout the Lawson Middle School gym as community members gathered with former students and staff to catch up with old friends, flip through old yearbooks, and dance the afternoon away.

Led by current students and staff, the stroll down memory lane was part of a “Walk to Remember” — an event held to let stakeholders bid their final farewells to the building before it is demolished later this summer.

“It’s important to preserve the memories,” Lawson Principal Kasey Bailey said. “There’s a lot of history with this school, but we’re very excited to move into the new building.”

Continue reading

HISD Construction Services rep follows in father’s footsteps

If you ask Zach Hoskins about his father, he’ll tell you that he has been nothing short of an inspiration and the motivating factor that lead him to work for the Houston Independent School District.

Since he was a child, Zach Hoskins has watched in awe as his dad — HISD Maintenance and Operations General Manager Al Hoskins — climbed the ladder of success, working his way up from a roofer assistant to senior management. Continue reading

Eastwood Academy library addition nearing completion

[photoshelter-gallery g_id=”G0000iZ4U8X2tu30″ g_name=”20180612-Eastwood” width=”600″ f_fullscreen=”t” bgtrans=”t” pho_credit=”iptc” twoup=”f” f_bbar=”t” f_bbarbig=”f” fsvis=”f” f_show_caption=”t” crop=”f” f_enable_embed_btn=”t” f_htmllinks=”t” f_l=”t” f_send_to_friend_btn=”f” f_show_slidenum=”t” f_topbar=”f” f_show_watermark=”t” img_title=”casc” linkdest=”c” trans=”xfade” target=”_self” tbs=”5000″ f_link=”t” f_smooth=”f” f_mtrx=”t” f_ap=”t” f_up=”f” height=”400″ btype=”old” bcolor=”#CCCCCC” ]

Eastwood Academy is set to open a new two-story library wing this August as crews put the finishing touches on the second and final phase of the school’s expansion and renovation project.

Installation of exterior masonry and mechanical, electrical, and plumbing systems have been completed, and window installation is set to wrap up this week. Crews are in the process of hanging sheetrock inside the addition, which will be followed by internal inspections and installation of internal fixtures and finishes.     Continue reading